Project Name: Carver/Wayne Elementary School
Date Completed: May 1998
Contract Amount: $4.35 Million
Project Type: Educational
Location: Mt. Olive, NC  
The Carver Elementary School, originally a $5.7 million dollar, 62,000 square foot project was constructed in two phases. The initial phase was brought in sufficiently under budget (4.9 million) to allow a negotiated change order which would permit the construction of an additional six classrooms, financed under the terms of the original project budget.